Eighth Example – Project Planning for Construction of 3-bedroom House

If the Project Manager has a costed project schedule and wants to know options for minimising the project duration, what advice should the Project Planner provide? Read on to see how all key information can be provided through the #TimeCostCurves program.

Figure 1: Costed project schedule setup for producing the TimeCostCurve. Overheads are assumed to be GH₵ 1,000 per day.

Figure 2: Normal conditions schedule. (Note that “$” symbol should be read as “GH₵” in this example for Ghanian currency)

Figure 3: Automated activity selection TimeCostCurve with task ID data points. By inspection, the order of activities being crashed can be rearranged manually as below to make a smooth TimeCostCurve, which would be the practical order of activity crashing.

Figure 4: Smoothed TimeCostCurve with Task ID data points.

Figure 5: TimeCostCurve with fully crashed data point (added manually)

Advise based on TimeCostCurve program:

Schedule: Duration (days): Cost (GH₵): Remarks:
Normal schedule 44 days GH₵ 101,156.35
Least-cost schedule 32 days GH₵ 96,130.11
Least-time schedule 28 days GH₵ 98,451.09
Fully-crashed schedule 28 days GH₵ 100,787.06 The added cost compared to the least-time schedule is of no benefit since the critical path cannot be further shortened.

Figure 6: Least-time schedule




Eighth Example – Project Planning for Construction of 3-bedroom House


Added August 18, 2019 under example, and timecostproblemsolved




Home Search TimeCostCurves TimeLapseGantt TimeVsCost Archives Feed AOA Contact Page
Solving The Time-Cost Problem On Your Projects Since 2019