Seventeenth Example – Engineering Project Example

If the Project Manager has a costed project schedule and wants to know options for minimising the project duration, what advice should the Project Planner provide? Read on to see how all key information can be provided through the #TimeCostCurves program.

Figure 1: Costed project schedule setup for producing the TimeCostCurve.

Setup assumptions for TimeCostCurve program:

Assumptions: Assumed Value: Remarks:
  1. Overheads:

£ 500/day Equivalent to about 2 full-time senior engineers
  1. Fixed (sunk) costs:

£ 16,000 Direct (normal) costs
  1. Crashing of activities by working 6 hours of overtime

Crash duration = 4/7*Normal duration (rounded to nearest day)

Crash cost = 7/4*Normal cost

8 normal hours + 6 overtime hours = 14 total hours. Therefore ratio is 8/14 or 4/7

Figure 2: Normal conditions schedule.

Figure 3

Figure 4: TimeCostCurve with crashed Activity ID’s at data points. NB: Cost (AUD) should read Cost (£)

Figure 5: TimeCostCurve with fully-crashed schedule data point. NB: Cost (AUD) should read Cost (£)

Advice based on TimeCostCurve program:

Schedule: Duration (days): Cost (£): Remarks:
Normal schedule 60 days 46,000
Least-cost schedule 56 days 45,125
Least-time schedule 47 days 49,063
Fully-crashed schedule 47 days 51,500

Figure 6: Least-time schedule

NB. If we change our assumption so that activities can only be crashed by working 2 hours of overtime (after a normal 8 hours), rather than 6 hours of overtime, then the resulting TimeCostCurve would appear as below:

Figure 7: TimeCostCurve with crashed Activity ID’s at data points. NB: Cost (AUD) should read Cost (£)