If the Project Manager has a costed project schedule and wants to know options for minimising the project duration, what advice should the Project Planner provide? Read on to see how all key information can be provided through the #TimeCostCurves program.
Figure 1: Costed project schedule setup for producing the TimeCostCurve.
Assumptions: | Assumed Value: | Remarks: |
---|---|---|
|
$ 9,000/day | |
|
$79,000 | Direct (normal) costs |
Figure 2: Normal conditions schedule.
Figure 3
Figure 4: TimeCostCurve with crashed Activity ID’s at data points
Schedule: | Duration (days): | Cost ($): | Remarks: |
---|---|---|---|
Normal schedule | 17 days | 232,000 | |
Least-cost schedule | 15 days | 226,000 | |
Least-time schedule | 15 days | 226,000 | Same as least-cost schedule since total cost curve is linear in this case |
Fully-crashed schedule | 15 days | TBD |
Figure 5: Least-time schedule