Case
Study – Substation Construction Plan as per P6 Example
prepare your: |
gives you these options: |
|
With tccB01 (.MPP file), you have access to utility
data for activities. This case study data is available through the
WYSIWYGcrowdsourcedutilitycurves online google
sheet
|
Figure 1: Button to Plot TCC’s Activity-on-Arrow Chart
Figure 2: Userform for selection
Figure 3: AOA Chart produced via Mermaid Live Editor
|
gives you these options: |
Gantt Chart prepared
Click x3
|
With tccB01 (.MPP file), you have access to utility data
for activities
In a few clicks, you have a schematic network
model of the project
|
Figure 4: Utility data assumed based on P6 example with progress
update at approx. 10% complete
prepare your: |
gives you these options: |
Gantt Chart with (minimum) 2 options per
activity:
|
With tccB01 (.MPP file), you have access to utility data
for activities
|
Normal Duration and Crash
Duration
|
User can import activities with preloaded utility
data of <= 20 options per activity
|
Normal Cost and Crash Cost
|
User can define their own utility options or make
use of preloaded options.
|
Indirect time-related overhead cost per
Project
|
Privacy of utility data available if User assigns
percentages rather than actual durations and
costs
|
Userform with options to plot your TimeCostCurve
For example, in this case, user input ‘-4’ to shorten the project by
4 days |
|
Resulting TimeCostCurve, with these notes
Indirect costs assumed to be $850/day is not large enough to
reduce the total project cost as it’s duration is being
compressed.
To compress by 2 days, activity ID 11 (Install Equipment) is
compressed
To further compress by 2 more days, activity ID 8 (Set
Foundation) is compressed
To further compress by 1 more day, activity ID 5 (Dig Cable
Trench) is compressed
To further compress by 3 more days, activity ID 14 (Lay Control
Cable) is compressed
To further compress by 1 more day, activity ID 17 (Remove
Equipment) is compressed
To further compress by 2 more days, activity ID 4 (Mobilise) is
compressed
All-Normal schedule is 58 days, $375,620
VS Fully-crashed schedule is 47 days, $445,837
|
|
Figure 5: note the differences between this fully-crashed network
diagram and the all-normal network (Fig. 3) |
Figure 6: Fully-crashed schedule
|
gives you these options: |
…should really check out |
Run the timecostcurves app (within tccB01.mpp file)
to plot the time-cost curve in MS Excel. Selection of tasks can be
automatic or manual
Sketch your project’s network model
(Activity-on-Arrow)
|
You just GOTTA get:
tccB01.mpp from timecostcurves.com |
has just helped you
Solve your Time-Cost Problem
Saving Days and Dollar$ on your next Project…all in a few
clicks |